Piper Aircraft Internship, Fall 2025

During a sixteen-week Fall 2025 rotation at Piper Aircraft in Vero Beach, Florida, I worked as a test engineer intern in the Test & Instrumentation department, within the Test Operations group that runs ground and flight testing. I handled two Engineering Work Orders (EWOs), a fatigue test on PA-28 vertical stabilizer spar joints and a pitot-static hose pull test, worked on an independent redesign of a rudder pedal force capture fixture, and completed Piper's rivet training.

Challenge

Every work order setup had to pass checks by my supervisor, the requesting engineer and a quality assurance representative before data collection could begin.

  • The spar joint fatigue test, which I had started in the summer, still had to finish its six-specimen program of 20 million cycles each and look for cracks around the torqued bolts. The old TestWare Elite (TWE) program had caused problems during the summer and wrote data files of about 2 GB.
  • The pitot-static work order needed the tension in each hose recorded while it was pulled in line with its connector, and the first fixture let the hose clamp slip.
  • The existing rudder pedal force fixture placed a small, roughly one-inch cylindrical block on a button load cell. Pilots had to aim their foot at that small area and sometimes bend over to look at it, which is risky when a pilot is task-saturated in flight.
  • The load cell sat where pilots with larger feet struggled to reach it, the rudder pads and brake pads were at the same height, and nobody could see inside the cylindrical flange to confirm that the block still touched the load cell.

Action

Spar joint fatigue testing

I ran the test on an MTS servo-hydraulic load frame with six PA-28 vertical spar specimens. Three were Type Design High Torque (TD HT) joints torqued to 90 in-lbs, and three were Low Torque (LT) joints torqued to 30 in-lbs.

ParameterValue
Cycle definition122.5 ± 6.2 lbf to 1225 ± 62 lbf and back
Frequency20–25 Hz
Total per specimen20 million cycles
Inspection intervalEvery 5 million cycles

At each interval I backed off the nuts with a dial-type torque wrench with a memory pointer, measured the holes, had an authorized inspector perform a surface eddy current inspection, and re-torqued the bolts to their rated value before the next block of cycles. I rebuilt the test in the Multi Purpose Elite (MPE) software from a company template, which runs long servo-hydraulic tests without crashing, and wrote a new MATLAB script to process its data files.

Pitot mast and hose pull test

After the work order was revised, I connected the pipe to a flat aluminum stock through a 7/16 in. threaded hole instead of using the full pitot mast. I TIG welded an aluminum tube to a flat base to make the support frame. The hose clamp slipped because there was no shaft inside it to grip, so we moved the clamp to the other end of the pipe and inserted a screw for it to bite on. A small safety cable loop then let me pull the hose with a fish scale and read the force in pounds. I ran five pulls on the pitot hose and five on the static hose.

Rudder pedal force capture fixture

With a colleague, I kept what worked in the old fixture and changed only the four problems:

  • A rectangular plate that tapers to a small sphere replaced the small block, which enlarged the foot contact area while reusing the existing button load cell.
  • The load cell moved up, and a center block filled the cavity between the fixture and the concave pedal so the load still went into the rudder hump without flexing.
  • The rectangular pad sits higher than the brake pads, so the height offset leaves room to reach the brakes.
  • A peep-hole in the flange lets the team check the contact and look for wear over time.

To calibrate the button load cell, I clamped it in line with a 5000 lbf (22 kN) reference load cell using a C-clamp and read both through their own software. The calibration gave a linear relation, with a gain and an offset, that converts the button load cell's output in volts into force in lbf once the fixture is installed in the airplane.

Rivet training

I completed the three-day riveting course at Piper's Harry Brubaker Training Center, where production employees train before they work on the floor. On a training coupon, I drilled #30 holes for a BJ-4 rivet install and set BJ rivets with a rivet gun and bucking bar. Alongside the course, I learned nut plate installation and Hi-loc installation and removal, and I practiced looking up hardware by MS, NAS and AN standard numbers in Piper's internal database.

Result

  • The fatigue test ran continuously for about four months. I delivered six raw .txt data files with the peak and valley loads in lbf and the cycle count, along with inspection photos, back-off torque videos, test logs, notes and the MATLAB scripts. Quality signed off, and the work order was closed.
  • Switching from TWE to MPE cut each data file from about 2 GB to about 200 MB, which made post-processing much easier.
  • The hose pull tests measured between 15 and 21 lbs of tension. I recorded the values in the work order's table and attached a photo of the setup.
  • The rudder pedal force fixture was delivered for the Test Operations team to use in Piper's experimental airplanes. Its photos and data are confidential.
  • The rotation taught me that an improvement rarely needs a redesign from scratch, that the end user's top pain points should drive the design, and that a 3D-printed proof of concept can hide problems with tap drills, plate thickness and tolerances that metal parts will expose.

A sample MPE data file lists the cycle count and the axial load valley and peak values in lbf.